Function
Loadings of a predefined Load Group are copied or moved to another Load Group or deleted. When loadings for each construction stage are created for a construction stage analysis, copying or modifying the previously defined load groups may prove to be more convenient.
Call
From the Main Menu select [Structure] tab > [Group] group > [Change] > [Change Load Group]
Input
The [...] button to the right of Change Load Group : review Load Group Table
Options
Copy : copy the load data included in Source Group to Target Group
Move : move the load data included in Source Group to Target Group
Delete : delete the load data included in Source Group
Boundary Group
Source : original group
Target : destination group (inactivated when Delete is selected)
The [...] button : click to prompt the Define Load Group dialog box to add or modify groups.
Item : select the types of loadings to be copied, moved or deleted.